Does an IOD take between 6-8 months to obtain, as builders claimed?


OR


Answered on November 08, 2017
  • share
  • It is pre-requisite to obtain NOC's from the department of Chief Fire Officer (CFO) and Traffic and coordination department of the Municipal corporation of greter mumbai ( assuming area falls in the jurisdiction of MCGM), this usually takes about 30 days. Post issue of NOC's plans are submitted for the concession approvals from the Municipal Commissioner and subsequently it is submitted to the Building Proposal department of MCGM, which after thorough scrutiny sanctions plans and issue IOD. Whole process takes about 4/5 months in the current scenario.