305 people including me bought flats from the government scheme and did a full payment. Now this has been delayed for 12 years on flimsy demand of the third party certificate of no addition or alteration. But the RWA president is refusing to give us a selling deed saying that it is purely a matter between the seller and the buyer. For how long can CGEWHO delay this conveyance deed? Also, can the deed be delayed on such pretext?


OR


Answered on November 08, 2017
  • share
  • If, the flats are sold on ownerhsip basis, then the conveyance cannot be delayed at all and in fact under the provisions of the real estate and regulation act, the conveyance has to be effected immediately once more than 50% of the total units in the building has been sold and such purchasers have made the full payment of the consdieration amount.