Results for #Maha


facebook twitter linkdin

display picture
Answered on November 08, 2017
  • share
  • All under construction projects that have not received completion/occupancy certificate as applicable or shall not receive prior to July 31st, 2017 shall mandatory need to register with MahaRERA

    facebook twitter linkdin

    display picture
    Answered on December 03, 2017
  • share
  • Mumbai DCR Regulation 51(i) states: Apart from residential use,  Customary Home Occupation shall be permitted in buildings, premises or plots in a purely residential zone. 

    "Home occupation" is defined as customary home occupation other than conduct of eating or drinking place offering services to the general public customarily carried out by a member of the family residing on the premises with...

    (View more)

    facebook twitter linkdin

    display picture
    Answered on November 08, 2017
  • share
  • Flat buyer can log on to MAHA RERA to check if the project is duly registered. Flat buyer can also demand from the Promoter the Project Registration No. under RERA and then verify from MAHA RERA website.


    facebook twitter linkdin

    Answered on November 08, 2017
  • share
  • ( Source : maharera.mahaonline.gov.in) Yes, the layout of the real estate project has to be approved. However, the promoter may include some buildings in his application of registration where apartments are proposed and the Building approvals are pending. Building Approval for the apartment...
    (View more)

    facebook twitter linkdin

    display picture
    Answered on November 08, 2017
  • share
  • An abandoned project having Commencement Certificate and not having Occupation/Completion Certificate is required to be registered under MAHA RERA or RERA. If the project is abandoned and the promoter does not apply for registration, in such case alottee/s can approach RERA authority. In case the project is abandoned prior to the stage of Commencement Certificate, it will not come under RERA as...
    (View more)

    facebook twitter linkdin

    display picture
    Answered on November 08, 2017
  • share
  • The rate of interest payable by the promoters to the allottees or by the allottees to the promoters, as the case may be, shall be the State Bank of India highest Marginal Cost of Lending Rate plus two percent: Provided that in case the State Bank of India Marginal Cost of Lending Rate is not in use it would be replaced by such benchmark lending rates which the State Bank of India may fix from t...
    (View more)

    facebook twitter linkdin

    display picture
    Answered on November 08, 2017
  • share
  • The Promoter shall submit the application in that behalf to the Registrar for registration of the Co-operative Housing Society under the Maharashtra Co-operative Societies Act, 1960 or a Company or any other legal entity, within three months from the date on which fifty one per cent of the total number of allottees in such a building or a wing, have booked their apartment.

    facebook twitter linkdin

    Answered on November 08, 2017
  • share
  • ( Source : maharera.mahaonline.gov.in) In accordance with notifications issued by Urban Development Department of Government of Maharashtra, MR & TP Act is applicable to all the districts of Maharashtra. Hence, all areas of Maharashtra a...
    (View more)