Our society is locate in Parle (w), Mumbai. Builder mentions that we need to take a railway NOC since we are close to train station. Is that a requirement?


OR


Answered on November 08, 2017
  • share
  • If the Plot is within 30mtrs from the Railway Boundary and is shown in the D.P.Remarks as affected by Railway Buffer then NOC is Mandatory.